Irvine Regional Park Maintenance Building Replacement Project

Project Location:

Irvine, CA

Project Description:

For more than 80 years, the 475-acre Irvine Regional Park has been maintained by a large crew of Orange County employees and volunteers working from an outmoded collection of dilapidated shop buildings, storage facilities and offices. Design for the new Irvine Regional Park Maintenance Building Replacement Project began in 2008 and included the demolition of the five existing maintenance facility buildings and construction of three buildings: an office building, a maintenance building, and a shop building. The site improvements included new electrical service, fire service, and bio treatment/infiltration trench WQMP. During the design phase, obtaining a LEED Certification became an obvious choice to ensure that the new facility would be water and energy efficient, would be constructed out of sustainable materials, that the natural setting would be considered and honored, and that the indoor environment would promote optimum efficiency from the employees. The new Irvine Regional Park Maintenance Facility became the Orange County Park system’s first LEED Certified buildings.

RBF Consulting, a Michael Baker International Company was contracted as the Construction Management firm for the Design-Bid-Build project.  During the project development/design phase of the project the CM Team went over and above analyzing the program phasing, bid alternates, the commitment to safety and quality, building consensus with the maintenance team to facilitate an expedited construction schedule, and management of the environmental mitigation measures to the site.

Project Justification:

As its first LEED Certified building, the Irvine Regional Park Maintenance Facility represents the future of construction with the Orange County Parks system. The CM Team’s commitment to sustainability standards was demonstrated by working closely with the Design Team and Contractor’s LEED GA to incorporate construction materials, methods and practices to deliver a LEED Certified project, exceeding expectations and delivering a Certified LEED Silver project (1000009805). The CM Team demonstrated the depth of resources and flexibility on the Irvine Park Maintenance Facility Construction Project by providing a separate constructability review and construction estimate of the potable water system construction upgrades project that would serve the Maintenance Facility, LEED Oversight and Qualified SWPPP Practitioner Services, and a constructability / bidability review of the Maintenance Facility, which involved several meetings with all the stakeholders.

The CM Team suggested that temporary facilities be erected, in lieu of the proposed phasing of the facility, and expedited construction duration by 25%. Key to the success of the cost control was the document review, mandatory pre-bidding, addendum coordination and issuance – which led to the bid presenting well under the Architect’s estimate by more than 30%. The CM Team’s commitment and attention to safety paid off with no recordable injuries throughout the construction period.

Special Circumstances:

The major obstacle to overcome was to complete the project within the schedule requirements of the owner. Bad weather, challenging plan check coordination, and unforeseen septic tanks that required abandonment were poised to set the project back. The CM Team, in collaboration with the engineers and design teams, created time-saving solutions to keep the project on schedule. Effective communication between the Architect, CM Team and plan check engineers to effectively coordinate the deferred submittal process.

Project Attachments:

See additional information below.

Award Citation::

The Irvine Regional Park Maintenance Building Replacement Project replaces five 80 year-old maintenance facility buildings in Irvine Regional Park with three Certified LEED Silver structures. These are the first LEED Certified buildings in the O.C. Parks system. The project was completed early and under budget.

Suggested Award Summary:

For more than 80 years, the 475-acre Irvine Regional Park has been maintained by a large crew of Orange County employees and volunteers working from an outmoded collection of dilapidated shop buildings, storage facilities and offices. Design for the new Irvine Regional Park Maintenance Building Replacement Project began in 2008 and included the demolition of the five existing maintenance facility buildings and construction of three buildings: an office building, a maintenance building, and a shop building. The site improvements included new electrical service, fire service, and bio treatment/infiltration trench WQMP. RBF Consulting, a Michael Baker International Company was contracted as the Construction Management firm for the Design-Bid-Build project. 

As its first LEED Certified building, the Irvine Regional Park Maintenance Facility represents the future of construction with the Orange County Parks system. The CM Team’s commitment to sustainability standards was demonstrated by working closely with the Design Team and Contractor’s LEED GA to incorporate construction materials, methods and practices to deliver a LEED Certified project, exceeding expectations and delivering a Certified LEED Silver project (1000009805).

Project Awards

Burris Pump Station Project, Phase 1Skimming the Waters of Newport HaborSunset Ridge ParkLake Forest Sports ParkCoyote Creek Class I BikewayThe Anaheim Regional Transportation Intermodal Center (ARTIC) Corona del Mar Water Transmission MainSanta Ana River Interceptor (SARI Line) Relocation ProjectState Route 57 Northbound Widening (Central Phase)20 Story Office Tower and 8 Story parking Structure @ 650/670 Newport Center DriveTustin Ranch Road ExtensionBalboa Boulevard BeautificationPark PlaceSR 57 Widening North SegmentAnaheim Regional Transportation Intermodal Center (ARTIC)Irvine Regional Park Maintenance Building Replacement ProjectSand Canyon Avenue Grade SeparationSR-57 ImprovementsNewport Forcemain ProjectEmergency Roof Stabilization, Tustin Hangar 1Lower Santa Ana River Reach 9 Phase 2B ProjectNewport Beach Civic Center & ParkCity of San Clemente Recycled Water Expansion ProjectGroundwater Replenishment System Initial ExpansionCerritos Avenue Reconstruction and Sanitary Sewer Improvement Project Bristol Street Improvements Phase IINew Ocelot Exhibit at the Santa Ana ZooNewport Beach's Harbor Litter Removal ProjectBrookhurst Street Widening ProjectI-5/SR-74 Interchange Improvement ProjectOso Creek Multi-Use TrailPCH/Del Prado Street ImprovementsMarina ParkNewland, Edinger, and East Garden Grove Wintersburg Storm Channel Confluence SystemGobernadora Multipurpose BasinLincoln Avenue Widening over the Santa Ana RiverGilbert Street ImprovementsLAGUNA BEACH FESTIVAL OF ARTS FAÇADE/ENTRANCE PROJECTALEGRE AFFORDABLE APARTMENTSCow Camp Road Design – Phases 1A & 1BWest County Connectors ProjectWaste to Energy - Bowerman Power ProjectGlassell Yard Campus Stormwater Low-Impact Development Retrofit ProjectEsencia, Rancho Mission ViejoIrvine Boulevard Pedestrian BridgeOrange County Water District La Palma Groundwater Recharge BasinStanton Central ParkJeffrey Open Space Trail Emerald Bay Entrance WideningPeters Canyon (Wash) Channel Water Capture and Reuse Pipeline Project 91 Express Lanes Pavement Rehabilitation and CMS ReplacementMemory Lane Park, Santa AnaLa Pata Extension Project SR-91 Westbound WideningNewport Beach Country Club Clubhouse400 Spectrum Center Drive Soil Nail WallMyra 3 Stormwater Pump StationSunset/Huntington harbour Dredging and Waterline ProjectHuntington Beach Senior Center In Central ParkNewport Boulevard WideningCrown Valley Park Channel Entry ImprovementsAnaheim Convention Center Betterment VIIMackay ParkTesoro Zone II and Zone B Water FacilitiesPark Avenue Bridge over Grand CanalI-5/La Novia RoundaboutDairy Fork Wetland and Habitat RestorationJeffrey Road Park n' Ride Lot Expansion ProjectTustin-Rose Grade Separation Project, Part of the OCTA OC Bridges Grade Separations ProgramArgyros Girl Scout Leadership CenterWagon Wheel Creek Restoration and Stormwater ManagementOCTA OC Bridges ProgramABC Green Home 3.0 ProjectLaguna Beach Festival of the Arts Grounds RenovationOrtega Highway Emergency Repair ProjectThe Tracks at BreaBaker RanchCity of Buena Park Fire Station No. 61Arlington Drive Bioswale & Dry Weather Diversion ProjectAltair IrvineVillage Pond Park/Veterans Park RenovationMid-Basin Injection: Centennial ParkAgua Chinon CorridorTarbut V’ Torah Phase III & Phase IVRancho Mission Viejo Joint-Use PavilionI-5 HOV Improvement Project between Avenida Pico and Avenida Vista HermosaOrange County Great Park Sports ComplexCrawford Canyon Road Drainage Improvements & ReconstructionSouth Cove DevelopmentGreat Park Ice & FivePoint ArenaLido House HotelBroadcom Corporate Campus (now FivePoint GatewayWest Orange County Water Board Feeder No. 2 RelocationNewhope-Placentia Trunk Sewer Replacement Project State College Boulevard Grade SeparationLos Patrones ParkwayRancho Mission Viejo Multipurpose Path Urth Caffe - OrangeSR91 Widening from SR-55/91 Separation to SR-241/91 SeparationEdwards Lifesciences Parking Structure

Candidate Awards

Natalie A. Meeks, P.E.Tasha M. Kamegai-KaradiYazdan (Yaz) T. Emrani, P.E., Byron Tobey, PE, QSD, LEEP APEric WalkerGidti Ludesirishoti Victoria PilkoPratanu GhoshSteven R MarvinPhil Jones, PE Joshua Nelson, PEVictor AguirreKenneth H. Rosenfield, PEGeorge A. Jurica, PETom BogardRavi Shah, PE, QSP/QSDAmy Choi, EITElizabeth Ruedas, EIT, ENV SPMujahid ChandooRoxanne FollisAmir Aghakouchak, Ph.D., M-ASCE, P.E.Fred MinagarJeffrey Okamoto, PEHarvey GobasChloe GhariosKevin Onuma, P.E.Ryan ChamberlainDr. Adrian MooreMichael Pierce, A.M.ASCERemi Candaele, PE, MS, QSD/QSP, M.ASCEThomas A. Broz, P.E., S.E, F.ASCEKaren Cervantes, S.M.ASCEIsamar Escobar, A.M.ASCEKevin Kondru, P.E., M.ASCEDouglas J. Johnson, P.E., M.ASCEJeremy Redman, PhDChristopher HaireMojgan Hashemi, P.E., M.ASCEOC Report Card Executive CommitteeSteven J. Huff, P.E., M.ASCEWilliam Bennett, P.E., M.ASCEBruce Phillips, P.E.Brad Dybel, PEBryant WongGyssela (Jazzy) Quinabo, E.I.T.Nestor Godinez, PEProfessor Joel LanningElizabeth RuedasDave LoweWei KooBill LawsonAmber GanapathyBob KallenbaughState Senator Josh NewmanGary UrbanDr. Sudarshan KurwadkarClint Isa, PEJason Fix, PEChirath "Chuck" KarunathilakeAmber ShahAshlyn AlexanderJohn C HoganMarionne Philline LapitanDr. C.T. Bathala, PhD, P.E.Kevin Du Mont, P.E.Ziad Mazboudi, P.E., D.WRE, MBADavid Frattone, P.E.Lisa BartlettJennifer BohenGyssela (Jazzy) Quinabo, E.I.T.Andrew Pham, PE, City of IrvineMatthew Cugini, PE, CaltransFarzian Zareian, Ph.D.Thomas T. Kim, PEDon Hoppe, PEDoug Staley, PERavi Shah, PEMark Vukojevic, PEDavid Naish, PhDLacy KellyGary L. Miller, PEKenneth RosenfieldAndrew Easterling, EITSteven L. King, PESteven R. Marvin, PEJose G. Jimenez Jr.
CEC

Contact Us


Please contact the Board of Directors at .(JavaScript must be enabled to view this email address) if you would like to speak with an ASCE OC Branch representative, or the webmaster if you have any questions or comments about this web-site.

ASCE OC Branch

1405 Warner Avenue, Suite B
Tustin, CA 92780

(714) 258-8306

Website

ASCE Los Angeles Section

(714) 258-8306

Website

ASCE National Society

1801 Alexander Bell Drive
Reston, VA 20191

1-800-548-ASCE

Website

Stay Connected


Copyright © 2019 ASCE Orange County, California Branch. All Rights Reserved.

Designed and developed by Jub Jub Interactive.